NIPIGAZ to be general contractor on Gazprom Neft Moscow refinery CRU
The Gazprom Neft Moscow Refinery has entered into a preliminary agreement with NIPIGazpererabotka (NIPIGAZ) to undertake extensive
construction and installation works for the commissioning of the
refinery’s Euro+ combined
refining unit (CRU). Initial costs of these works are expected to be approximately $313 MM (excluding VAT), with final costs to be confirmed following presentation of full
project documentation by NIPIGAZ as general contractor.
Construction of the Euro+ CRU represents a key
project in the second phase of Gazprom Neft’s full
modernization of the Moscow
refinery. The Euro+ facility is intended for primary oil
refining, for the production of high-octane Euro 5 fuels, and for the production of vacuum gasoil. The facility is expected to be commissioned in 2018.
Once fully operational, the Euro+ facility is expected to increase
refining capacity at the Moscow refinery to 12 MMtpy. In addition to improving energy efficiency and workplace safety, the plant continues to reduce its
environmental
emissions.
Construction of the new facility will allow Gazprom Neft to decommission several obsolete installations and increase running time between repairs from two to four years, ensuring the further stabilization of the fuel market around the
capital.
Russian enterprises and companies remain actively involved in the
modernization of the Gazprom Neft
refinery. AEM-Technology, in particular (part of the machine-building division of state enterprise Rosatom), has already begun production of a major plant for the Euro+ facility.
For subscriptions or a demo:
Sam Hassaniyeh
Subscription Executive
Phone: +44 203 4092242
For questions or to give feedback:
Thad Pittman
Senior Researcher
Phone: +1 (713) 525-4605
Download our brochure today!
Project News